Every figure on this site is an estimate from inputs you can see and change. This page states the formulas, where the default numbers come from, how they are rounded, what is left out, and how often the data is checked.

How the monthly estimate is built
Milesper day × 30.4Battery kWh× kWh per 100 miWall kWh÷ (1 − loss)Cost× rate, split home / public

Energy

Vehicle efficiency is entered battery-side, as kWh per 100 miles, which is what cars and EPA labels report. What the meter sees is more, because some energy is lost in the charger, cable and battery management. We call that the charging loss and default it to 12%.

Wall energy = miles × (kWh per 100 miles ÷ 100) ÷ (1 − loss). A month is 30.4 days.

Cost

Money is kept in whole cents. Each cost component is rounded once, when kilowatt-hours meet a rate; totals are sums of those integers. Per-mile and percentage figures are derived from the totals and rounded only when displayed.

Charging time

Hours = battery kWh × (target − start) ÷ (charger kW × (1 − loss)). Constant power is assumed; real sessions taper above roughly 80%.

Default data

What is not modelled

Verification

The calculation library has unit tests for boundary conditions and five reference scenarios computed independently in a second language with decimal arithmetic. Utility rates are re-read against their source documents in the first week of each quarter and whenever a reader or a rate-change notice points to a change.

Corrections

If a number on this site is wrong, tell us through the contact page with the source you are looking at. Corrections are made on the page, with the content-changed date updated; we do not silently rewrite history.